We have a brand new updated website! Click here to check it out!

US-77/ I-70 Interchange Update

KDOT logoThe Kansas Department of Transportation reports that:

If all goes well and the weather cooperates, traffic on US-77 at the I-70 Interchange at Junction City will be rerouted to more accurately resemble the final configuration of the new Divergent Diamond Interchange Tuesday, December 20, 2016.

The permanent signals are scheduled to be activated at the same time. Traffic will still experience temporary lane closures while curb and gutter, median caps, etc. are completed and for the removal of the temporary asphalt crossing no longer needed.

Plans call for final construction activity in the area of the interchange to be completed in the next few weeks weather permitting.

This interchange is near the Sapp Brothers/A&W location in Junction City.