Municipal Court Project 110 days Behind Schedule

The Junction City Municipal Court Project at 701 N. Jefferson is now 110 days behind schedule due to delays with a sub contractor on the project.

The metal building system manufacturer provided shop drawings that were repeatedly rejected by the City’s municipal buildingstructural engineering consultant. That approval process took approximately 30 days to complete placing the project farther out in the manufacturers production queue, creating the 110 day delay.

Tyler Ficken, City Clerk explained that the delay is not expected to cost the city anything.

“If for some reason the elongation of the period of time of the construction results in additional costs to the city, the city could pursue damages for the additional cost,” said Ficken.

Currently the project is on budget and is 28 percent billed out according to Ficken. The new completion date is projected to be July 19th.