After school let out Wednesday a number of the Fort Riley Elementary School staff traveled to the site of their new school, that is currently under construction, to receive an update and tour the construction site.
In April USD 475 broke ground on the new $22 million school being built to replace the 60 year old school currently in use. The new
76,700 sq. ft. school will have space for 500 K-5 students.
Currently the project is on schedule but it almost wasn’t when the original bids for construction came back $4 million higher than originally expected.
“We were able to value engineer about half that, $2 million, without changing the scope of the building,” said Bill Clark, the District’s Director of Business Operations. “The other $2 million we’re currently working with both the Office of Economic Adjustment out of Washington as well as the State of Kansas to help finish the cost of the other $2 million.”
Crews are currently in the brick and mortar phase of the project,”framing out the school and putting the brick and mortar up. Getting it enclosed so during the winter months they can get inside and really build the inside of the school.”
The school offers a number of features including an innovative library media center, mobile labs, wireless technology, and a gymnasium that will also serve as a tornado safe room built to FEMA standards to withstand 250 mph wind speeds.
Becky Coy has been the Principal at Fort Riley Elementary School for 21 years and said that when she found out that the school district was planning to build a new school her initial reaction was,”Wow! Can it be possible?”
“And the bigger question to that is, was it really going to happen? Because it took a lot of people, and it took a lot of time, and it took a lot of money to make that to happen. Over the period of time it came to be, and they always say patience wins out so definitely that was a sign, good comes to those who wait,” said Coy.
After the walk through she explained that the biggest thing she was trying to do was imagine what it will look like when it is complete.
“What I’m seeing from the walk through is the light. The sun light that is going to be coming in to our building. It’s going to be like fresh air to us. It’s almost like stepping up the professionalism as you walk through that building, it’s just going to enrich our learning.”
The new school is expected to be open in time for the 2015-2016 school year. Once the move is complete the former school building will be turned back over to Fort Riley.
The new school is the third new school built on Fort Riley in the past three years. Fort Riley Middle School opened in August and Seitz Elementary School opened for the start of the 2012-2013 school year.