The Metropolitan Planning Commission will be considering a special use permit request on behalf of Westar Energy to construct a large electric substation in southern Geary County.
The MPC has continued the matter to Thursday night’s meeting after first hearing
about it in December according to Dave Yearout, Director of Planning and Zoning.
“Because of issues about identifying specific haul routes that they will use on county roads to bring in the heavy equipment and the Planning Commission wanted to see that Public Works had the opportunity to work that through with Westar, and that’s been done,” said Yearout.
The haul route has been identified as US Hwy 57 from I-70 south to Clarks Creek Road, from Clarks Creek Road south to Old Stage Road, and back west on Old Stage road to Hawkinsmith Road south where the substation will be on the west side of the road.
Along that route there are five drainage culverts which were inspected by Kaw Valley Engineering who determined that the culverts would be able to handle the large loads that would travel down the route during construction.
A video inspection of the route was also done in order to have evidence of the condition of the road prior to the start of construction.
“During construction when that happens over the next couple of years, if there are incidents that happen as a result, we’ll have the documentation to be able to say,’No this deterioration occurred long before you came in,’ or ‘No you guys are the ones who caused this and you need to fix this and repair the bridges.”
Staff recommendation to the MPC is to recommend approval of the conditional use permit to the County Commission who has final say over the issue. The MPC meets Thursday night at 7 p.m. in the Municipal Building.