New Irwin Army Community Hospital to Open in Late Summer Early Fall

The new Irwin Army Community Hospital built on Fort Riley looks complete on the outside but contractors are still working on the inside to open it by late summer or early fall.

Col. Risa D. Ware, Commander of IACH explained that the hospital is approximately 98 percent complete.

Photo From the Official Irwin Army Community Hospital Facebook Page.
Photo From the Official Irwin Army Community Hospital Facebook Page.

“They’re doing all of the commissioning, all of the testing of the electrical systems, emergency lights and that sort of things. Contractor and Corps of Engineers estimate that will probably take us through the end of March maybe mid-April,” explained Ware. “Then we move all of the furniture, all of the equipment all of that sort of stuff which takes about four to five months.”

The new hospital was built just east of the current facility which was built in 1958, and went through it’s last renovation in 1978. The new facility is roughly 170,000 sq. ft. larger than the old one and has cost approximately $404 million to build.

Ware explained that the new facility will be top of the line and have the latest technology allowing the hospital to expand it’s services.

One area they are currently awaiting final funding for would be the new hospitals 10 behavioral health beds. In order to treat patients for behavioral health they first need to gain additional funding to provide nurses for that area.

“Our immediate higher head quarters has already approved it, we just have to get big Army to approve the funding. This is important not only for the Army but for Kansas because Kansas has a significant shortage of in-patient behavioral health beds.”

Ware said that she does believe that the funding will be approved, but it may be a few months before that happens.

 