Phase one of the terminal expansion project at Manhattan Regional Airport is expected to wrap up in January.
That portion of the project was originally expected to be completed by August
of this year but there were a number of delays according Peter Van Kuren, Airport Director.
“Weather early in the project prevented the slab from being poured, and of course that then prevented steal from being constructed and just ended up delaying things,” said Van Kuren. “There’s been small design areas that have needed modification, nothing significant, but when you encounter those things it requires additional time to complete.”
Phase one of the project includes the expansion of the passenger loading and holding area, and security screening area.
Van Kuren said that Phase two of the project is expected to get underway as soon as Phase one is complete and the weather will allow them to do some outside work.
He explained that phase two will include expansion of the passenger unloading zone and,”the baggage claim area and the rental car concessions will be housed in that area.”
The $15.8 million project is being funded through grants from the Federal Aviation Administration and City of Manhattan funding. It is expected to be completed in the fall of 2015.