There is progress in the effort by USD 475 officials to reduce the cost for building the new Fort Riley Elementary School.
The school district’s Business Opeations Director Bill Clark reported Monday that the anticipated $4 million in higher than anticipated bids for the project have been reduced down to about $2 million through a value engineering process. The Board of Education has agreed to the reductions.
Clark said officials have also approached the federal Office of Economic Adjustment to request additional money for this project because of the increase in construction costs for the project. “And we’ve also gone back to the State of Kansas, and asked them for some adjustments as well.” No final action has been taken by either the OEA or State at this point.
As part of the effort to reduce costs Clark said there have also been discussions with Fort Riley officials about anti-terrorism force protection requirements on the schools, and whether the post is willing to reduce some of those requirements. That request is still under review.