Due to street improvements that began on June 19th in Grandview Plaza, patrons will need to utilize the back entrance for access to Stacy’s Restaurant on 118 W Flint Hills Blvd.
To access Stacy’s Restaurant, enter on the backside via Continental Drive – the front entrance will be blocked.
The Kansas Department of Transportation (KDOT) said the planned work will be between Continental Drive and State Street.
Construction on 40B/K-57 and J Hill Road will be completed in two phases. Phase one will include construction of the drainage structure extensions and widening of the entrances on the north side of 40B/K-57/Flint Hills Blvd. Phase two will have Continental Drive closed to construct the tie-in with a mill and overlay of the existing pavement under flagger control.
During the construction of the project, an 11-foot westbound lane will be maintained on 40B/Flint Hills Boulevard.
The project is expected to be complete in early August.